Road projects being implemented in Dar es Salaam as part of Tanzania’s preparations to host the 2027 Africa Cup of Nations (AFCON) have reached an average completion rate of 50 percent, with the government directing contractors to accelerate work.
Minister of State in the Prime Minister’s Office responsible for Regional Administration and Local Government (PO-RALG), Prof Riziki Shemdoe, said the projects were progressing well but contractors needed to increase the pace of construction to meet deadlines.
Prof Shemdoe made the remarks on August 24, 2026, after inspecting road construction works serving venues that will host matches and training sessions during AFCON 2027.
He inspected projects in Kigamboni, around Benjamin Mkapa Stadium, Leaders Club and along the Mbweni–Major General Isamuhyo Stadium route.
The inspection showed varying levels of progress across the projects. Works in Kigamboni had reached 75 percent, while those around Leaders Club stood at 70 percent.
Road works around Benjamin Mkapa Stadium had reached 20 percent, with the Mbweni–Major General Isamuhyo route also at 20 percent.
Prof Shemdoe directed contractors to work around the clock to raise the overall implementation rate to more than 60 percent by August 30.
The directive comes as Tanzania steps up preparations for the continental tournament, which it will co-host with Uganda and Kenya.
But beyond AFCON preparations, residents say the road projects could provide a much-needed solution to persistent transport challenges in their neighbourhoods.
A Mbweni resident and Malindi Estate Street Government representative, Maria Bilia, said residents were pleased to see construction progressing, arguing that better roads would make it easier for people to move between their communities and other parts of the city.
“We are happy to see the roads being constructed because they will help reduce the transport challenges we have faced in this area,” she said.
Ms Bilia also asked Prof Shemdoe to convey residents’ appreciation to President Samia Suluhu Hassan for investing in road infrastructure linked to the AFCON preparations.
She said residents had observed contractors working day and night, which she described as an indication that the government was pushing to complete the projects on time.
Malindi Estate Street Chairperson in Mbweni Ward, Kinondoni Municipality, Selina Mkonye, said residents were also pursuing a broader infrastructure plan that goes beyond the tournament.
She said the community had developed a five-year plan to improve 30 kilometres of roads to tarmac standard and another 60 kilometres to gravel standard.
According to Ms Mkonye, the AFCON-related projects had provided additional momentum to the community’s efforts to improve roads and ease movement in the area.
The government says the road works are aimed at improving access and traffic flow to stadiums and training venues that will be used during AFCON 2027, while ensuring the infrastructure delivers long-term benefits to residents.
The projects currently under implementation include the construction of Taifa Road, covering 1.3 kilometres, Litapwasi Road (0.43 kilometres) and Sotele Road (0.2 kilometres) to concrete standard.
Other works include the 0.7-kilometre Yanga Road, also to concrete standard, the 0.5-kilometre Dahomey Road to tarmac standard and improvement of the 0.8-kilometre Mbalizi Road.
The programme also includes improvements to the VVIP parking area at Major General Isamuhyo Stadium.
With the August 30 target approaching, attention will now turn to whether contractors can meet the government’s demand for faster implementation while maintaining the quality of the infrastructure.
For Dar es Salaam residents, however, the ultimate measure of success will extend beyond AFCON 2027: whether the upgraded roads translate into easier travel, better access and reduced congestion in the communities they serve.