Kadogosa orders removal of Tanga Airport project supervisors over delays

 

Minister questions use of mobilisation funds as construction progress falls behind schedule

By Our Correspondent

 The government has ordered changes to the supervision team overseeing the rehabilitation and expansion of Tanga Airport after concerns over slow construction progress and inadequate mobilisation of project resources.

Minister for Works Masanja Kadogosa directed the Tanzania National Roads Agency (TANROADS) to immediately remove the engineer supervising the project and appoint a replacement capable of ensuring effective oversight and timely completion.

He also ordered the removal of the contractor’s representative, accusing him of taking his responsibilities lightly and failing to comply with government instructions.

The directives were issued on November 21, 2026, during an inspection of the project, where Mr Kadogosa questioned why construction activities were progressing slowly despite changes to the project scope.

He said the contractor had been expected to achieve full mobilisation of equipment, personnel and other resources by February, but the level of preparedness remained below expectations.

The Minister also questioned how the advance payment released to the contractor for mobilisation had been spent, demanding accountability for the public funds.

“The contractor was paid an advance payment for mobilisation. If mobilisation has not been achieved to the required level, where has the money been spent? This is an issue that requires answers,” he said.

The concerns raise questions about project management and the effectiveness of supervision, particularly the extent to which government officials have monitored the contractor's performance and enforced contractual obligations.

Mr Kadogosa said the government would not tolerate negligence or poor performance in public projects, stressing that infrastructure investments must deliver value for money and meet agreed implementation schedules.

He directed TANROADS to strengthen project monitoring, warning that the contractor's shortcomings should not give government officials an excuse to neglect their supervisory responsibilities.

He said both the contractor and public officials must be held accountable for their respective obligations to ensure the airport project delivers the intended benefits to residents of Tanga and the wider country.

Meanwhile, Tanga District Commissioner Edwin Methew, representing the Regional Commissioner, said the inspection had provided encouraging indications of progress.

He assured the Minister that the challenges identified would be addressed in line with the directives issued, pledging that the project would be completed to the required standards and within the agreed timeframe.