By The Respondent Reporter
The Managing Director of
Tanesco, Mr. Lazaro Twange, began a working tour across Dodoma on July 18,
2025, to evaluate the progress of several major electricity infrastructure
projects.
These include the transmission
line from Zuzu to Mbande, an ambitious underground power distribution network
in the Government City, and the construction of a new central power receiving
and distribution substation.
Speaking from one of the project
sites, Mr. Twange provided updates on the milestones achieved so far. He noted
that the 33kV transmission line stretching from Mbande to Zuzu is nearly
halfway completed, currently standing at 48.35%.
Meanwhile, the underground
distribution system in Ihumwa—a cornerstone of the Government City’s future
electrical grid—has reached 64% completion. This modern infrastructure, once
finalized, is projected to cost over TZS 50.09 billion.
“These projects are crucial to meeting the rising power needs of Dodoma,” Mr. Twange emphasized. “But more importantly, they’re about laying the foundation for a smart, resilient, and future-ready grid.”
During the inspection, he urged
contractors and project teams to pick up the pace, emphasizing that timely
completion would ensure residents and institutions start benefiting as soon as
possible. His tone was firm but optimistic, encouraging a sense of urgency, yet
appreciating the complexities involved.
A highlight of his visit was the
inspection of the new power receiving and distribution substation located in
central Dodoma. According to Mr. Twange, construction on the facility has
crossed the 80% mark and is expected to be fully operational by early September
this year.
“This is more than just a
substation,” he said. “It’s a game changer for Dodoma’s city center. The
previous infrastructure simply couldn’t keep up with demand. Once this is up
and running, it will significantly improve electricity delivery across central
areas, reducing outages and boosting reliability.”
Mr. Twange didn’t shy away from
addressing the hurdles the projects have encountered, particularly in terms of
financial constraints. However, he commended Tanesco engineers, supervisors,
and the contractors on the ground for their dedication and resourcefulness in
navigating the challenges.
He concluded with a message of
reassurance and purpose: “We’re committed to ensuring that these projects, once
complete, provide stable and reliable electricity not just for Dodoma but also
for surrounding regions like Morogoro.
This is how we drive
development—through energy security.” Mr. Twange’s site visit reflects not just
oversight, but a deeply personal commitment to progress—an effort to bridge
ambition with execution as Tanzania continues to modernize its power
infrastructure.